St Barbara Paste Plant

Client

St Barbara Limited

Location

Leonora, Western Australia

Completion

2008

Requirement

  • Construction of Paste Plant
  • Construction work to be completed in a significantly reduced timeline to meet client deliverables
  • Build to start prior to design completion

Highlights and Achievements

  • Development of strategies to ensure tight fabrication and construction timelines were adhered to
  • Escalation of manufacturing process to enable fast delivery
  • Relied on significant experience in Paste Plant construction to pre-empt issues and planning
  • Local workshops in Kambalda and Kalgoorlie provided efficient project support schedules
  • Successful completion of the project at a depth of 1400m in a confined and oppressive environment

Benefits for Client

  • Solid and ongoing relationship with CPC provided confidence in project delivery on time
  • Project delivery in short timeframe allowed early start to operations and production