Structural and Platework Rigging Sub Contract
Client: Pacific Industrial Company (PIC)
CPC Engineering Goldfields was engaged by Pacific Industrial Company to carry out the erection and installation of structural steel and plate work from the Secondary Crushing through to the Milling Area, this formed part of the Anglogold Ashanti/Independent Group JV Tropicana Project 390km North East of Kalgoorlie.
The Work on site Included:
- Supply of Labour and equipment
- Take delivery and unloading of all structural steelwork, including all beams, columns, bracing, rafters, purlins, girts, brackets, bolts, handrail sections, grating and all other components
- Erection of all structural steelwork as detailed in the Construction Drawings inclusive of all beams, columns, bracing, rafters, purlins, girts, brackets, bolts, handrail sections, grating and all other components included within the PIC scope
- Supply of craneage and access equipment
- Erection and installation of all plate work items in sequence with the erection of the structural steel frame
- Penalisation of structural modules prior to installation
The project was carried over a 9 month period with manning levels peaking at 69 personnel with support from the Kalgoorlie workshop and was carried out safely and efficiently with no LTI’s
CPC Engineering delivered the following services and personnel:
- Project Manager
- Project Engineer
- Site Administration
- Structural, mechanical and rigging Supervision
- Fitters, Boilermakers, Riggers, Crane Drivers and Trade Assistants
- Cranes and Rigging
- EWP’s